Polyurethane arch installation is a technical process used to frame curved wall openings and construct architectural passages without adding structural load. Engineered from rigid closed-cell polyurethane with a density of 150-220 kg/m³ (production target ~160 kg/m³), these decorative components require accurate radial layout, correct adhesive application, and mechanical anchorage. Polure arch profiles offer dimensional stability for both interior and exterior wall applications when installed according to precise field protocols.

Step-by-Step Application

  1. 1. Yüzey Hazırlığı ve Alan KontrolüMontaj yapılacak kemer içi veya duvar kavis yüzeyi toz, yağ ve gevşek katmanlardan arındırılmalı, yüzeyin tamamen kuru olduğundan emin olunmalıdır. Tahmini Süre: 15-20 dakika Sık Yapılan Hata: Nemli veya tozlu yüzeye doğrudan yapıştırma yaparak yapıştırıcının tutunma mukavemetini düşürmek.
  2. 2. Şablon Çıkarma ve Ölçü KontrolüKemer yayın açıklığı ve tepe yüksekliği ölçülür; düzensiz kavislerde karton şablon hazırlanarak duvar eğimi birebir profile aktarılır. Tahmini Süre: 20-30 dakika Sık Yapılan Hata: Sadece taban genişliğini ölçüp yayın dairesel sapmalarını hesaba katmamak.
  3. 3. Gönye Kesim ve Kuru ProvaPoliüretan profiller açılı gönye testeresi ile 45 derecelik açılarla kesilir ve yapıştırıcı sürülmeden önce duvar yüzeyinde kuru prova yapılarak birleşim noktaları kontrol edilir. Tahmini Süre: 15-25 dakika Sık Yapılan Hata: Kuru prova yapmadan profilleri kesip doğrudan yapıştırıcı sürmek.
  4. 4. PU Yapıştırıcı UygulamasıProfilin arkasındaki kanallara ve ek birleşim yüzeylerine kesintisiz poliüretan (PU) montaj yapıştırıcısı sürülür. Silikon gibi uygun olmayan malzemeler kesinlikle kullanılmaz. Tahmini Süre: 10-15 dakika Sık Yapılan Hata: PU yapıştırıcı yerine esnekliği yetersiz nötr veya akrilik silikon kullanmak.
  5. 5. Yüzeye Yerleştirme ve Mekanik SabitlemeProfil kavis hattına bastırılarak oturtulur. Ardından 30-50 cm aks aralıklarıyla matkapla delik açılarak dübel ve vida ile mekanik sabitleme zorunlu olarak gerçekleştirilir. Tahmini Süre: 20-30 dakika Sık Yapılan Hata: Yalnızca yapıştırıcıya güvenip vida ile mekanik sabitleme adımını atlamak.
  6. 6. Ek Yeri Macunu ve ZımparalamaVida başları ve birleşim ek yerleri poliüretan uyumlu macun ile doldurulur. Macun kuruduktan sonra 180-220 grit zımpara ile yüzey tamamen pürüzsüz hale getirilir. Tahmini Süre: 30 dakika (kuruma süresi hariç) Sık Yapılan Hata: Macunun tam kurumasını beklemeden zımpara yapmak veya kalın zımpara ile profili çizmek.
  7. 7. Astar ve Boya UygulamasıTamamlanan yüzeye ihtiyaç halinde opsiyonel astar katı atılır. Dış cephe uygulamalarında zorunlu olarak UV dayanımlı boya ile 2 kat boyama yapılarak işlem bitirilir. Tahmini Süre: 20-30 dakika (katlar arası kuruma hariç) Sık Yapılan Hata: Dış cephede UV koruması olmayan standart iç cephe boyaları tercih etmek.

Material Performance and Structural Non-Load-Bearing Limits

Rigid polyurethane arch components feature a closed-cell structure engineered to operate safely within a temperature tolerance of -100 °C / +80 °C. With a target production density of approximately 150-220 kg/m³ (production target ~160 kg/m³) and a water absorption rate under 1%, these profiles resist environmental degradation and dimensional shift. However, installers must treat all polyurethane columns, curves, and arch profiles strictly as decorative, non-load-bearing elements that require full wall support.

Required Tools and Structural Adhesive Selection Criteria

Proper field installation requires specific tools to achieve clean joint alignments and secure mechanical attachment:

  • Polyurethane (PU) assembly adhesive (Silicone adhesives are strictly forbidden due to lack of structural shear strength)
  • Mechanical fasteners: Wall plugs (dowels) and corrosion-resistant screws
  • Miter saw or hand saw with fine-tooth blade
  • Sanding sheets (180-220 grit)
  • Joint putty and spatula
  • Measuring tape, flexible curve ruler, and level

Arc Radius Measurement and Multi-Piece Joining Protocols

Accurate radial alignment is critical when executing curved transitions. Installers must measure the spring point width and the total rise height of the opening rather than relying on standard geometry. Multi-piece arch assemblies must be mock-fitted on a flat surface to check seam continuity before applying adhesive. Joint alignment across multi-segment arches requires consistent miter angles to prevent steps along the inner and outer radii.

Surface Preparation and Moisture Considerations

The installation substrate must be completely dry, clean, and stripped of loose plaster or dust. Because rigid polyurethane features a water absorption rate below 1%, moisture trapped behind an unsealed installation cannot migrate through the profile. For exterior wall applications, applying a weather-resistant base layer and utilizing UV-resistant exterior paint is mandatory to protect the material from long-term solar degradation.

Sanding, Priming, and Final Coating Requirements

Profiles are supplied with a factory-applied primer layer. While an additional field-applied primer coat is optional depending on local jobsite requirements, it is not strictly prohibited. All filled joints must be sanded smooth using 180-220 grit sandpaper once the putty has cured. Final finishing requires two coats of high-quality paint, with UV-stabilized paint formulations being strictly required for any exterior exposure.

Dış Cephe Koşulları ve Yüzey Boya Boyutları

Polure ürünleri fabrikasyon olarak astarlanmış yüzeyle sevk edilir. Montaj sonrası ek yeri macunu ve zımpara yapılan bölgelerin kapatılması için ek astar uygulaması opsiyonel bir teknik tercihtir; 'astar gerekmez' şeklinde kesin bir kural koymak doğru değildir.

Dış cephe kemer ve kavis uygulamalarında, poliüretan malzemenin uzun yıllar iklim koşullarına dayanabilmesi için UV dayanımlı dış cephe boyası kullanılması şarttır. En az iki kat halinde uygulanan UV filtreli boyalar, malzemenin yüzey kalitesini korur ve sararmayı engeller.

Sıkça Sorulan Sorular

Why is silicone adhesive prohibited during polyurethane arch installation?

Silicone lacks the long-term structural shear strength required for dense polyurethane products; a polyurethane (PU) assembly adhesive must be used.

Is mechanical screw attachment mandatory for arch profiles?

Yes, mechanical anchorage using screws and wall plugs is mandatory alongside structural PU adhesive to guarantee permanent installation safety.

What sanding grade should be used on polyurethane joint seams?

Use 180-220 grit sandpaper to achieve a flush, smooth transition without gouging the factory-primed profile surface.

Is an additional primer required over factory-primed polyurethane arches?

Factory primer comes pre-applied on Polure profiles; applying an additional coat of primer on-site is optional based on project specifications.

Fabrika çıkışlı astarlı profillere tekrar astar atmak gerekir mi?

Fabrika çıkışlı ürünler astarlı olarak gelir; ancak macun ve zımpara yapılan birleşim noktalarının emiciliğini dengelemek için ek astar atılması teknik bir opsiyondur.